DAM
PERMIT PROJECT
If you would like to see photos related to the project, please click on the
link.
News as of April 2001
We have received the Dam Operating Permit and fully comply with all State
regulations.
January 2001
The Emergency Action Plan has been approved by the Illinois Department of
Natural Resources. Copies are on file with local agencies. The
Operating and Maintenance Plan has been revised. IDoNR will publish
a Public Notice informing local residents of our Permit Application. We
expect to be granted a Dam Operating Permit in February.
October 2000
The concrete construction for the stilling basin is complete.
DeMeester's have completed restoration of the landscaping around the spilway
and grass seeding.
Attended a two day seminar in Marion, IL for instruction on how to prepare
and Emergency Action Plan.
An Emergency Action Plan is beeing drafted.
August 2000
The Association approved a resolution for a loan
to fund the project.
Year End 1999
The Illinois Department of Natural Resources, Office of Water Resources,
requires that we obtain an "Operating Permit" for our dam. To comply
with their requirements, we had to build an energy dissipator at the base
of the spillway. At our AGM in July 1999, it was agreed that we should
proceed with this project, and obtain a loan for financing.
First we had to get IDOT to agree to some minor design changes.
-
We had several meetings with Jim Gastel of Gastel and Associates, our consulting
engineer.
-
Gastel & Associates completed a full survey of the dam and adjacent lot
lines.
-
Structural drawings were prepared to incorporate the changes from the original
design.
-
The necessary forms were prepared for the permit application and submitted
to IDOT on September 24th 1999.
-
Application form NCR426.
-
Survey of dam "as built".
-
Sheet 3 form the original drawing of the dam, prepared by Carl Thunman in
1973, red-lined to show the proposed stilling basin.
-
Proof of the Associations financial capability. 1997 tax returns.
-
A time line for the project.
-
Operating and Maintenance Plan revised 9/21/99.
-
On November 4th we were told by IDOT that:
-
The emergency action section in the Maintenance Plan needs to be revised
to meet new guidelines. It will be necessary to attend a class for
this. Date unknown. Waiting for IDOT to set this up.
-
IDOT will issue a permit after the plan is updated. GOOD NEWS!
-
The application was submitted to other agencies responsible for endangered
species, historical preservation and the Army Corps of Engineers. We
heard nothing from these agencies, so after 30 days we were free to proceed.
-
A "Request to BID" package was prepared and sent to six local contractors
capable of performing the work. The Board of Directors met in February
to review the bids, and selected Civil Constructors bid of $51,298.
-
Subject to weather, the work is scheduled to start mid-summer (August). We
will agree on a date two weeks in advance. The lake level will be lowered
1 - 2 ft.
-
A work party will be required to remove weeds and several small trees before
work begins.
Last updated 15 April, 2001.